In this phase, the package is installed in a development or test area, and the
stakeholders get together in one room to compare the features and functions of the package
with the needs identified in the system analysis phase of the Selection stage. Any
required functionality that is not included in the package is identified, in addition to
any changes to the package that are required. If necessary, the system analysis may need
to be revisited, to incorporate the functions of the package.
The primary participants in this phase are the core team and all additional
stakeholders identified as extended team members and scheduled in the Fit/Gap Analysis
Planning phase.
Package Installation
The package is installed in a development/test area for functional
appraisal, using University data. |
|
Use Cases and Scripts
Use cases are specific examples of business processes. Scripts are
step-by-step instructions for appraising functionality. At this time, there are neither
templates nor samples for these items. |
  |
Updated Business Process Models
These models show the triggering event, the primary and secondary outputs, and the inputs
of the desired system. These models must be updated from the original Business Process
models to reflect the customized package, and any new processes must be modeled using
Visio templates available on the M drive. Note: If you do not have Visio on your
machine, you will not be able to use the template. In this case, you can use the PC in the
hallway where Visio is installed. |
  |
Updated Business Process Document
This document is the text companion to the Business Process models. Update the original
document with the new processes, and change the previously-defined processes as required. |
  |
Updated Activity Flow Diagrams
This diagram documents the flow of activities for a business process or sub-process.
Update existing activity flow diagrams as needed to reflect the customized package. If
there is an attached Word document describing the activity flow, be sure to update that
too. |
  |
Updated Extended Entity Object Model
The extended object model includes aggregates and inheritance, as
needed. If the package is very different from the projected system defined in System
Analysis, you will have to create a new model; otherwise, you can update the existing
model to reflect the customized package. This model is updated or created in Visio. |
  |
Object Life Cycle Models
If new objects have been added, or an existing object has a different
life cycle in the package than the projected system, new models may be required. These
models are created in Visio. |
  |
Customization Report
This is a brief explanation of the adaptations and adjustments required to make the
package work for Princeton. At this time, there is no template and no sample for the
Customization Report. |
  |
Updated Project Plan with Phase Section
for Logical Design
The project plan produced in the System Analysis phase is updated with information on
deliverables, resourcing, and schedules gleaned from the Fit/Gap Analysis. In addition, a
phase section is produced for the Logical Design phase and attached to the project plan. |
  |
Methodology Compliance Form
This form is initialized by the project team, and completed by a
methodology representative who has reviewed the project documentation and found it
acceptable. It is completed in Word.At this time, no sample is available. |
  |
Recommendation Form
This form is completed by the project team, and contains the
recommendation to the approving authority on whether or not the project should continue.
The form is completed in Word.At this time, no sample is available. |
  |